650kW Binder woodfuel boiler - Dunstan High School, Alexandra - Dunstan High School is a 560-pupil secondary school serving a large rural catchment in and around Alexandra - replacing their existing 1.4MW coil boiler with a single, high efficiency 650kW Binder woodfuel boiler, the school saw a reduction in boiler size of over 50%, with the same level of performance in their heating system. This delivered significant cost savings, greater system efficiencies and lower air emissions.